We could use 3/4 minus for the lane surface from the firing line to the berm (that's my preference). Previously we have used 1 1/4 minus or 1 1/2 minus. Once the eco blocks are set (to 6 ft high and 12 ft wide), we pack pit run rock around them, however we may want to pack them with 1 1/2 minus instead. Then the final 2 ft deep is 1/4-10 Washed gravel (same as highway pavement gravel but washed. We've gotten the 1/4-10 from ODOT for lanes 2 & 3.yeah my gal is asking me now if its just 3/4 minus. so yes details will help. No promises but im hopeful she can get owners to help possibly. shes the accountant/payroll etc and good friends w ownership, so i like the odds.
Fingers Crossed!
I'll try to dig up the quantities as soon as I can.